The north and south expansion joints for Structure 1 were installed and set in place at the end of November. Expansion joints are a critical component of a bridge, and allow the structure to expand and contract in response to temperature changes, traffic loads, and other environmental factors. Bridges are large structures made of materials like steel and concrete, which naturally expand in hot weather and contract in cold weather. Without expansion joints, these movements could cause cracking, buckling, or structural damage. Additionally, the North expansion barriers were cast in concrete on Jan 20, 2026 and the South expansion joint barriers are anticipated to be cast in concrete early February, 2026.
Looking north at the Structure 1 bridge progress. November 20, 2025.
Structure 2
Girder Installation
Girder installation of the steel girders for Structure 2 is being undertaken in several phases. The first phase of this work was completed on October 6, 2025, and the second phase was completed on January 29, 2026.
Looking northwest at the girder Structure 2 after the first phase of girder installation work. November 14, 2025.
A steel girder is lifted into place during the second phase of installation work. January 26, 2026.
Structure 3
Looking east at the progress on the northbound bridge’s substructure (Structure 3). December 9, 2025.
Following the completion of piling work in October, the formwork and rebar for structure 3 was installed and concrete was poured in November. Formwork is a temporary structure built to shape and support concrete as it cures, rebar remains in the concrete after curing to add strength.
In December, the installation of both the east and west bridge abutments was completed.
What’s Ongoing?
Structure 2
Work continues installing bearings. These are mechanical components that transfer and distribute force across different components of the bridge’s structure. The installation of temporary structures to support concrete as it cures, known as deck form work, is also ongoing.
Structure 3
Work is ongoing to install formwork for the West Abutment Wingwall. This is a retaining wall that extends from the sides of the bridge’s support structure (abutment). Wingwalls retain the soil or fill material leading up to the bridge, helping prevent erosion or sliding that could affect stability.
A view of the work decks that will be used when installing exterior wingwall formwork. January 15, 2026.