A temporary relocation of the northern multi-use pathway, crossing the Southland Drive bridge, has been implemented to accommodate construction activities related to the new structure.
Pathway relocation map.
What's Ongoing?
MSE Wall Work
Precast panels (panels that are fabricated off-site and installed onsite) are currently being installed to complete the MSE Walls to begin substructure work for the new Southland bridge for the ultimate road alignment.
Southland MSE Wall Progress, July 11, 2025.
Anchor Wall construction under the existing Southland bridge is ongoing. An anchor wall is a structural component designed to provide lateral support and stability to adjacent elements—typically retaining walls, abutments, or approach slabs.
What's Completed?
Substructure Work
Pile extensions for the new bridge structure have been completed. Adding extensions to bridge piles is done to reach the depths required to support large bridges, while helping to make the transport and installation of materials easier by enabling components to be delivered in smaller segments.
Looking south at the Southland pile extensions and MSE Wall progress, August 20, 2025.
Utility Work
Trenchless crossing work was completed in this area during the day.
Trenchless crossing activities in Southland. July 11, 2025.